Ticino Opens New Visletto Bridge Nearly Two Years After Deadly Floods
A new bridge over the River Maggia has opened in Switzerland’s southern canton of Ticino, restoring a permanent road connection to the upper Maggia Valley almost two years after catastrophic flooding swept away the original structure.
The new Visletto Bridge was officially inaugurated on Saturday, October 31, and opened to motor traffic at 4:30 p.m., according to the cantonal authorities. Its completion marks a major milestone in the recovery of a region severely affected by the storms and floods of June 2024. However, reconstruction work across the valley is continuing.
A permanent connection after the 2024 disaster
The original bridge at Visletto was destroyed during the night of June 29–30, 2024, when exceptionally severe storms caused the Maggia to rise and sweep away the structure. The loss of the crossing disrupted road access to the upper Maggia Valley and temporarily left several side valleys without normal road connections.
The disaster caused widespread damage across the region, including to roads, buildings and essential infrastructure. Seven people died in the Vallemaggia area, while one person remained missing, according to reports on the aftermath of the floods.
The destruction of the Visletto crossing became one of the most visible reminders of the scale of the disaster. For residents, the bridge was not simply a transport route: it was an essential connection between communities in the upper valley and the wider canton.
A temporary solution was put in place in July 2024. The Swiss Army installed a replacement bridge, allowing road access to be restored within weeks of the floods. But the temporary structure came with significant restrictions. Vehicles were limited to a maximum weight of 32 tonnes, traffic was restricted to one lane, and the speed limit was 20 kilometres per hour.
Those limitations made a permanent replacement necessary, particularly because the crossing serves local residents, businesses and essential services.
A new bridge designed with erosion protection in mind
The replacement bridge has been built slightly upstream from the location of the original crossing. The change in alignment is intended to improve protection against erosion and reduce the risk of damage from the river.
The completed structure extends for more than 150 metres and incorporates a reinforced-concrete deck. It also accommodates infrastructure needed to support the valley, including water supply, wastewater disposal, electricity and telecommunications networks.
That integration is particularly important because the 2024 disaster damaged more than the road crossing. The floods also affected technical infrastructure and utility connections, forcing services to operate through temporary arrangements. The new bridge therefore serves as both a transport link and a route for essential networks.
The cantonal government selected the VISLÈ consortium to carry out the project. Its design was chosen following a procurement process that considered technical quality, landscape integration and environmental impact. The original project specifications described a five-span structure, with a combination of steel and reinforced concrete.
The canton has financed the bridge in full. The latest report on its opening puts the construction cost at CHF10.5 million. An earlier cantonal announcement in June 2025 had cited a contract offer of CHF8.45 million, illustrating that the figure reported at the project-selection stage was not the final cost stated at the opening.
Reconstruction extends beyond the crossing
Although the reopening restores a crucial road connection, the authorities have stressed that the bridge does not mark the end of the region’s recovery programme.
Further work is planned to improve flood protection, develop facilities for pedestrians and cyclists, and redevelop parts of the Visletto settlement. These measures form part of a wider effort to make infrastructure and local communities more resilient to future natural hazards.
The scale of the wider recovery effort is substantial. In June 2025, the Ticino government outlined urgent restoration measures for the Maggia Valley and Leventina, including road repairs, natural-hazard protection, river-management work, restoration of water infrastructure and updates to hazard-zone planning.
The same announcement recorded 50 significant natural events in the affected areas, including debris flows, riverbank erosion and smaller landslides. More than 100 buildings were affected, with 15 completely destroyed or severely damaged. The canton estimated that its financial commitment for restoring cantonal infrastructure and supporting local authorities would reach approximately CHF45 million to CHF50 million.
A progress report published in July 2026 offered another indication of how much work remained. Fourteen of 30 reconstruction projects had been completed by that point, while the Visletto Bridge was still among the major projects approaching completion. The estimated overall reconstruction costs for the Maggia Valley were around CHF100 million, according to the report.
A milestone, not the end of recovery
The reopening is a practical improvement for people who depend on the road every day, but it also carries significance for communities still dealing with the consequences of the floods.
In October, Cevio mayor Wanda Dadò described the reconstruction as a rapid process that had delivered a new, stable bridge in just over two years. She also stressed that other projects were continuing and would require further time and effort. ticinonews.ch
The distinction matters. Restoring a major crossing can reconnect communities and make everyday travel easier, but it cannot by itself repair damaged landscapes, replace lost homes or resolve every infrastructure problem caused by the disaster.
The new bridge is therefore both an achievement and one stage in a longer recovery. Its position further upstream and its role in carrying essential utility networks reflect an effort to improve the valley’s infrastructure, rather than simply reproduce what existed before the floods.
For the upper Maggia Valley, the return of a permanent road connection is a significant step towards normality. The remaining challenge is to ensure that the wider reconstruction programme delivers lasting protection and reliable services for communities exposed to the power of the river and the risks of extreme weather.